03/04/2014 17:12
Pushkin and Dilijan tunnels to be repaired
39 million drams is required for design work and field supervision of road facilities in 2014, but only 18 million drams was allocated from the state budget. In order to allocate the remaining sum, during its session today the government redistributed funds in the 2014 state budget and made changes to its previous decisions, according to the press office of the government.
28 million drams has been allocated for design work on major repairs of Pushkin and Dilijan tunnels in 2014 and the next few years.
Large-scale repairs and technical control will be done on 4.5-km Goris road of Yerevan-Goris-Iranian border motorway and several sections of Yerevan-Sevan-Ijevan-Azerbaijani border motoray.
The decision did not necessitate changes in the revenues and expenditures of the state budget or allocation of additional financial resources.